In Coventry & Warwickshire Development Partnership LLP v Avison Young (UK), the court considered four common grounds for resisting enforcement of an adjudicator's decision:
whether the adjudicator acted outside of his jurisdiction by adopting his own valuation;
whether his reasons were adequate;
whether reliance on third-party material gave rise to a breach of natural justice; and,
whether any defective parts of the decision could be severed.
The judgment provides useful guidance on the limits of these challenges and reinforces the high threshold parties must overcome to avoid enforcement.
Coventry & Warwickshire engaged Avison Young as project manager and supervisor under an NEC3 ECC Option A contract concerning the development of an industrial and logistics park at Gateway South in Coventry. A dispute arose between the parties in relation to the certification of the sums due on the monthly payment applications. Coventry & Warwickshire alleged that Avison Young:
significantly over-valued the amounts that were due to the contractor,
wrongly accepted the contractor’s assertion of the extent of the work performed, and
failed to identify the defects in the work that had been completed.
Avison Young rejected this position and Coventry & Warwickshire subsequently referred the matter to adjudication.
The adjudicator adopted a less conventional analytical approach, structuring his analysis around the valuation and certification process. In doing so, questions of breach and causation were considered as integral aspects of the valuation exercise rather than as distinct stages in isolation.
The adjudicator reached his decision on 13 February 2026, determining that Avison Young failed to properly assess the amount due in accordance with the contract and failed to perform its duties with the required standard of skill and care. The adjudicator therefore awarded Coventry & Warwickshire circa £8.7 million plus interest as damages. However, Avison Young subsequently resisted enforcement of the decision, giving rise to proceedings before the Technology and Construction Court
Following adjudicator's decision, Avison Young challenged enforcement on four grounds relating to jurisdiction, adequacy of reasons, natural justice and severance. The court rejected each argument and enforced the decision.
This decision reinforces the Technology and Construction Court’s pro-enforcement approach to adjudication. For construction professionals, it highlights that:
Challenges based on jurisdiction, adequacy of reasons or natural justice remain difficult to establish and will only succeed in exceptional cases.
Adjudicators are entitled to reach their own conclusions, including by accepting parts of each party's case and rejecting others.
A decision will not be unenforceable simply because an adjudicator adopts an analytical approach that differs from that advanced by the parties.
Attempts to reargue the merits of an adjudicator's conclusions under the guise of severance are unlikely to be favoured by the court.
Ultimately, the judgment serves as a reminder that adjudicators' decisions will generally be enforced, even where a party disagrees with the outcome, provided the adjudicator has acted within their jurisdiction and in accordance with the requirements of natural justice.