What new regulations have been introduced under the Planning in Wales Infrastructure (Wales) Act 2024?

read time: 2 min
25.06.25

On 18 June 2025 the Welsh government laid down five statutory instruments to support the delivery of Wales’s new Significant Infrastructure Project (SIP) consenting regime under the Infrastructure (Wales) Act 2024 (IWA). 

These Regulations flesh out the outline in the act, giving more detail on each stage of an application for an infrastructure consenting order (ICO). They also cover relevant fees, compulsory acquisition requirements and the approach to optional SIPs (or schemes directed into the SIP regime by the Welsh ministers). 

The Fees Regulations and the Miscellaneous Provisions Regulations are subject to final sign-off by the Senedd, in which case, they are subject to change (and some of the provisions may indeed need changing and require industry comment). Also, two further sets of Regulations are anticipated to be published in due course relating to changing, revoking and challenging ICOs.

In short, much of the content in the Regulations follows closely the detail in the IWA, which closed in December 2024. On 24 June, the Welsh government issued its response to this Consultation and the draft Regulations reflect their final position on how they want the regime to operate. A big gap in all of this is the supporting Guidance document which the Welsh government has explained will clarify a number of the outstanding questions around how the Regulations will be applied in practice.

Those familiar with the Developments of National Significance (DNS) regime will know how broadly the DNS Regulations have been drafted (particularly in terms of the Welsh ministers’ and Inspectors’ ability to deviate from the seemingly fixed processes and timescales). The SIP Regulations are no different. What is clear is that there is a lot of flexibility built into the Regulations in which case users of the system need to be careful because there are practical realities (e.g. resourcing in Local Planning Authorities (LPAs) and statutory consultees) which will mean the discretion to deviate from the process set in the Regulations will be used more frequently.   

In this article we highlight the five regulations that will support the SIP consenting regime and outline the key points and timescales.

The regulations that will support the SIP consenting regime

  1. The Infrastructure Consent (Pre-Application and Application Procedure and Transitional Provisions) (Wales) Regulations 2025
  2. The Infrastructure Consent (Examination and Decision) (Procedure) (Wales) Regulations 2025 
  3. The Infrastructure Consent (Fees) (Wales) Regulations 2025
  4. The Infrastructure Consent (Compulsory Acquisition) (Wales) Regulations 2025 
  5. The Infrastructure Consent (Miscellaneous Provisions) (Wales) Regulations 2025

Key provisions of the Regulations

Commentary

The IWA and this suite of Regulations are the future for developing infrastructure in Wales. Those familiar with the DNS and NSIP regimes will recognise a lot of similarities of both in the SIP regime. Reading the Regulations, it feels like the Welsh government have followed their own mantra of including the ‘best of both’.  

As we have said before, the regime offers a significant number of new powers which can be used to unlock sites, not just powers of compulsory acquisition and access/surveying powers but also incorporating a raft of other consents in an ICO or disapplying other legislative requirements to facilitate the delivery of a project. The Regulations give the Welsh ministers and the ExA a lot of discretion in terms of process, procedure and timescales which may beg the question around certainty of the decision making process. However, one thing that is missing from the regime’s full picture is the supporting Guidance (as noted above). We would hope for further clarity in this document to address how the Welsh government envisages certain powers being used in practice.

The shift from a regime focussed on full planning permission (for DNS projects) compared to one offering a significant amount of flexibility with defined limits of deviation, as well as use of the Rochdale envelope concept (available to SIP projects) will need a mind-set shift for a number of practitioners and developers operating in Wales but ultimately it should put developers in that rare position of having both control and flexibility over the delivery of their projects. 

Get in touch with our planning and infrastructure team if you would like to discuss the changes in greater detail and what they mean for you. We will also be hosting a seminar to offer further insight into the new procedure, so keep an eye on our website for more details to be announced soon.

Sign up for legal insights

We produce a range of insights and publications to help keep our clients up-to-date with legal and sector developments.  

Sign up