The case of C G Fry & Sons Limited v Secretary of State for Housing, Communities and Local Government concerned whether Somerset Council could require an appropriate assessment at the reserved matter stage and whether they could refuse to discharge a condition on the grounds of lack of mitigation of potential impacts on a Ramsar site.
In this article we explore the key issues the Supreme Court considered to make its decision.
C G Fry applied for outline planning permission for a mixed use development in 2015 for 650 residential units and commercial and community uses, a primary school and associated infrastructure and land at Jurston Farm, near Wellington. This was split into eight phases. The development falls within the catchment area for River Tone which feeds into the Ramsar site of the Somerset Levels and Moors. The Somerset levels are also protected as a special protection area under the Conservation of Habitats and Species Regulations 2017 (Habitats Regulations).
Ramsar sites are protected wetlands, the protection arising from the Ramsar Convention and the Wildlife and Countryside Act 1981 - but not importantly, under the Habitats Regulations. However, the National Planning Policy Framework (NPPF) provides that Ramsar sites should be given the same protection as habitats sites, colloquially known as ‘European sites’.
In June 2020 Somerset Council granted reserved matters approval for the third phase of the development subject to 10 conditions. In August 2020 an advice note containing new scientific evidence was published by Natural England that called for greater scrutiny of plans in special area of conservation, special protection areas and Ramsar sites. This in part arose from the Dutch Nitrogen case heard in the European Court. This called for nutrient neutrality, to reduce nutrient loads impacting those protected areas. As a result of this advice, Somerset Council refused to discharge conditions on the reserved matters application pending an appropriate assessment under the Habitats Regulations.
In the High Court, which we summarised here, the court found that an appropriate assessment is required before the planning conditions could be discharged. The High Court dismissed the claimant’s argument that the NPPF does not make an irrelevant consideration into a relevant one, focusing instead on the purpose of the policy to protect the Ramsar site. The Court of Appeal agreed.
The Supreme Court considered two key issues:
Before setting out the court’s findings, by way of brief summary the key legislation and policy considered was:
| “3. Any plan or project … likely to have a significant effect thereon, either individually or in combination with other plans or projects, shall be subject to appropriate assessment of its implications”. |
|
“63.—(1) A competent authority, before deciding to undertake, or give any consent, permission or other authorisation for, a plan or project which— |
| “The following should be given the same protection as habitat sites.. (b) listed or proposed Ramsar sites” |
|
On the first ground the court agreed with the secretary of state, focusing on a purposive reading of the legislation to protect the reason the legislation was enacted. Regulation 63 of the Habitat Regulations applies to a wider variety of stages, including at reserved matters and condition discharge.
The directives were put in place to protect vulnerable wildlife and sites and ensure “careful scrutiny of development proposals likely to have an impact on such habitats with a view to minimising of avoiding such impact” . Appropriate assessments are a tool local planning authorities can use to provide such scrutiny.
The court disagreed with C G Fry’s submission that appropriate assessments only need to be carried out at the granting of permission stage, finding such an approach ‘unsustainable’. By placing the protective purpose of the regulations at the centre of the scrutiny, the court found that to limit the opportunity for an appropriate assessment to only at permission stage would defeat rather than promote and respect the wildlife.
The court further held that the Habitats Regulations deliberately broad language includes a wide variety of scenarios to respect the protective purpose of the legislation. As the Habitat Regulations do not expressly state that appropriate assessments do not apply to other planning stages, Somerset Council was not acting unlawfully in requiring it at the condition discharge stage.
For local authorities and developers, this reinforces that they ought to act cautiously when calling for protective measures for European sites, e.g. special area of conservation or special protection areas), and the judgement means no change to the current approach.
That is to say, where European sites are involved, appropriate assessment under the Habitats Regulations can continue to be required post grant of planning permission, for example at reserved matters or condition discharge stage.
On the second ground the court agreed with C G Fry. Somerset Council could not withhold the discharge of a condition to further another cause. There is no legislative backbone to the Ramsar protections, it's ‘just’ policy. Policy cannot make something which is immaterial to the discharge of a condition material. Therefore, in this case Somerset Council could not prevent discharge of a tree condition in other to further the unconnected prerogative of the protection of the Ramsar site.
Ramsar sites are protected under the NPPF, not the Habitat Regulations. This makes them fundamentally different to European sites within planning law. The courts key findings were:
If there were unmitigated impacts on a special area of conservation or special protection area, then a council could require an appropriate assessment and refuse to discharge a condition unless necessary mitigation was secured - this is not applicable to CG Fry.
However, if the site in question is a Ramsar site, and there are no issues pertaining to mitigation of a special area of conservation or special protection area, mitigation for impacts on the Ramsar site would have needed to have been secured at permission stage. It cannot be done at later condition discharge stage, unless there was a specific condition requiring it.
The finding on issue 2 is important. It will release sites that are ‘stuck’ in the system which have planning permission but have been unable to discharge pre commencement conditions due to the nutrient neutrality issue. Following the Supreme Court’s findings, such sites should not need to acquire credits to offset nutrient loads, or upgrade septic tanks, for those final approvals to be issued.
Developers may now wish to check any section 106 obligations or credit acquisition agreements to see whether funds or commitments can now be clawed back.
Whilst the judgement has been long anticipated, the situation is potentially to change in the near future. The House of Lords are currently discussing the amendments to schedule 6 of the Planning & Infrastructure Bill. One such amendment is to extend the Habitat Regulations to Ramsar sites, creating the statutory protection that Ramsar sites currently lack. This means the distinction made by the Supreme Court when addressing issue 2 may not stand beyond Christmas. Note this will not impact the rulings in relation to issue 1.
For further information, please contact David Richardson or Hannah Lewthwaite.
We produce a range of insights and publications to help keep our clients up-to-date with legal and sector developments.
Sign up