|
|
||
|
![]() Construction Industry Related Questions & Answers
Answer The courts have been fairly robust in enforcing adjudicators' decisions. The court will not generally look behind the decision for the reasoning used by the adjudicator, even if the decision appears to be wrong or there is an obvious error. Instances where the court have refused to enforce an adjudicator's decision include adjudications where there has been apparent bias on the adjudicator's part or where he has acted outside his jurisdiction. Question Answer For such an application to succeed it is important that the defending party does not take any step in the court proceedings (other than returning the "Acknowledgement of Service") such as serving a Defence. A party making such an application should consider whether it wants to bring another party brought into the proceedings such as a sub-contractor. This is possible in court proceedings but generally not in arbitration proceedings. It is also important to ensure that the arbitration clause being relied upon is properly incorporated into the contract as the court may reject the application to stay if there is not a clear and unequivocal reference to such a clause Answer The definition of a "dispute" has been the subject of some judicial interpretation by the courts (sometimes conflicting). The courts have recently given a very wide interpretation as to what will amount to a 'dispute'. Several heads of claim can fall under the umbrella of one dispute. Most adjudicators generally accept that the parties must bring a crystallised dispute to adjudication. In most cases that means that both parties have had an opportunity to give their different views on the matter prior to proceedings. However, if a party consistently fails to consider a matter put to them and requests for a response are met by silence then this is sufficient to amount to a 'dispute'. This approach should prevent what is called ambushing. This is where one party launches a claim against another in adjudication proceedings, which has not been previously received or considered by the recipient. In such circumstances it should be argued by the receiving party that the adjudicator does not have jurisdiction to deal with this new claim, as a dispute has not yet crystallised. Answer What is the position where there is no schedule of defects issued at the end of the defects liability period? In the case of Pearce and High Ltd v Baxter, it was held that in those circumstances where no schedule of defects was issued at the end of the defects liability period the employer still retained the common law right to employ another contractor and to recover damages for breach of contract on the part of the contractor. However, if the employer refused to allow the contractor to return to repair the defects, the damages would be restricted to the amount it would have cost the contractor to carry out the repairs. In any event, a contractor remains liable for any latent defects appearing after the defects liability period for a period of six years from the date of practical completion or twelve years where the contract is executed as a deed. Answer Under the regulations any person who has, by virtue of a contract or an obligation of any extent in relation to the maintenance or repair of non-domestic premises has a duty to manage the risk from asbestos. The duty to manage comes into force on 21 May 2004. However, those with such a duty are advised to start addressing the task now by:
Employers also need to consider training for staff and the provision of information, how they are going to manage contractors working in their premises and what to do when asbestos is discovered unexpectedly. Answer This should help to ease the burden on the Main Contractor in that payments to the Sub-Contractor will be falling due at the same time as payments under the Main Contract. The DSC also gives the contractor an additional four days for payment, the final date for payment being 21 days after the due date. This gives some breathing space between payments under the main contract and the sub-contract. There are changes, involving the alteration of retention and practical completion provisions as well as various new provisions which seek to encourage a more open and co-operative environment. There does not seem to be anything radically different about the DSC when compared with DOM/1 but it is presented in a more user-friendly way. Question Answer The Co-op employed structural engineers to provide assistance with some of the design. The engineers designed only part of the works and Henry Boot took over completion of the design and execution of the works, during which, water and soil flooded into sub-basement excavations. The Co-op sued both Henry Boot and the engineer for the damage they suffered. The Court held that Henry Boot had a duty to complete the design and execution of the works to the level of proficiency required by the contract that involved developing the concept design into one capable of being constructed. This required examining the design at the point at which it was taken over and concluding whether it was suitable. This decision serves as a warning to all contractors because the result confers upon them the responsibility to complete designs and execute works irrespective of any fault in the concept design. Therefore, be very careful when taking over preliminary designs completed by others. You should investigate thoroughly whether the designs are appropriate for the works. Question Answer To be eligible for Paternity Leave, an employee must have responsibility for the child's upbringing as well as being the biological father or the mother's husband or partner. Furthermore the employee should have worked for 26 weeks for his employer by the 15th week before the baby is due. Employees will be entitled to two weeks' paid leave, which will be paid at the rate of £100 per week, or 90% of the employee's average weekly earnings if he earns less than £100 per week. The leave must be taken within 56 days after the child's birth, or the expected week of childbirth. Employees will be able to take Paternity Leave in addition to their existing (unpaid) rights to Parental Leave Question Answer The moment the contractor becomes aware of a possible delay in completing the works by the contract completion date it should make an immediate application for an extension of time. Clause 25 of the JCT Forms of Agreement requires the contractor to make an application for an extension of time as soon as it becomes reasonably apparent that the works will be delayed. An employer can only deduct liquidated damages when the works have not been completed by the contract completion date. It is therefore important that the contractor gets an extension of time prior to contract completion in order to cut the risk of liquidated damages being deducted. Question
The general rule is that the paying party is required to give notice no later than 5 days prior to the final date for payment of its intention to withhold and/or deduct from the due amount. In the event of the paying party failing to serve the Withholding Notice upon the payee then the payee may have a sound argument for claiming in an Adjudication that its application for payment should be paid in full without deduction. Question
The new form of building contract for Partnering Contracts is known as `PPC 2000`. This contract is already being used by housing associations and the Government. The ethos is one of teamwork and an end to conflict and disputes. The PPC 2000 contract has a number of novel provisions. For example, it introduces the Partnering Advisor, Core Group and Problem Solving Hierarchy. There are also performance incentive payment mechanisms, such as key performance indicators. If they are achieved then the contractor will be paid more. However, if the contractor fails to meet the key performance indicators then he may be paid less. Is Partnering the way forward? What distinguishes Partnering from other procurement methods is more a state of mind than a new form of contract. Construction is a complicated business and where there is complexity there is room for disagreement. It remains to be seen whether Partnering is the panacea some would make it out to be. Time will tell. Question Answer If this does not work then there is Mediation. Mediation is becoming very popular and involves the appointment of an independent third party who acts as a go-between. A Mediation meeting will start with the Mediator sitting the parties around a table and allowing them a short period of time to set out their position. The parties will then be asked to go to their own rooms and the Mediator will shuffle between both parties rooms with a view to brokering a deal. The Mediation does not have any power to force an agreement on the parties. He is there is facilitate an agreement. From my own personal experience Mediation works and is to be encouraged. Question Answer If you have a `Construction Contract` evidenced in writing and formed after 1st May 1998 then a dispute arising out of the contract may be referred to Adjudication and the Statutory Scheme will apply where there are not adequate provisions in the contract. The Adjudication is started by the Referring Party serving a Notice of Intention to Refer and at the same time making arrangements for an Adjudicator to be appointed by making an application to one of the nominating bodies within 7 days of service of the Notice of Intention the Referring Party is required to serve its Notice of Referral which is effectively its claim document. The Adjudicator will then give directions which will in all probability give the Other Party an opportunity to respond. The Adjudicator may also call a meeting of the parties to obtain further information. The Adjudicator is required to issue his decision within 28 days of the service of the Referral Notice and his decision is enforceable through the Courts. The Statutory Scheme does not apply to Construction Contracts where the works are in connection with a residential property, where one of the parties will have his or her principle place of residence. Question Answer The moment the contractor becomes aware of a possible delay in completing the works by the contract completion date he or she should make an immediate application for an extension of time, even if at that stage there has been no delay. Clause 25 of the JCT Forms of Agreement require the contractor to make an application for an extension of time as soon as it becomes reasonably apparent that the works will be delayed. In my experience two many contractors leave it far to late to make applications for an extension of time and this can cause all kinds of problems. The biggest problem is the deduction of liquidated and ascertained damages. The Employer can only deduct liquidated damages when the works have not been completed by the contract completion date. This is why it is important for the contractor to get an extension to the completion date at the earliest possible opportunity in order to cut the risk of liquidated damages being deducted. Question Answer The rate to be used for interest which starts to run between 1st July and 31st December of any year is the Bank of England dealing rate in force on 30th June which has just passed. The rate to be used for interest which starts to run between 1st January and 30th June of any year is the Bank of England dealing rate on 31st December which has just passed. Further fixed sums penalties are payable in addition to interest. For a debt of less than £1,000 the penalty is £40. For a debt of £1,000 or more, but less than £10,000 the penalty is £70 and for a debt of £10,000 or more the penalty is £100. Prior to 7th August 2002 there were statutory provisions that provided for the payment of interest but its implementation was limited to small businesses who had 50 or few employees. Question Answer Where loss and expense has been incurred a written application should be sent to the Architect giving notice that direct loss and/or expense has been incurred. The application should be made as soon as it has become or should reasonably have become apparent that the regular progress of the works has been affected. In the application the Contractor should submit such information and details as should reasonably enable the Architect to form an opinion as to whether or not the Contractor is entitled to loss and expense. Upon receiving the application, together with the supporting information and details the Architect is required to ascertain the amount of loss and expense due to the Contractor. The sum ascertained should be added to the Contract Sum. Question Answer To start the process the Contractor is required to serve a written Notice on the Employer stating that he or she is interfering with or obstructing the issue of a certificate and that in the event of the Employer continuing this default for 14 days from receipt of the Notice then the Contractor will serve a Notice of Determination of Employment. The Notice should be served by actual delivery or by registered post or by recorded delivery. In the event of the Employer ignoring the Notice and not remedying the default then after a period of 14 days from service of the Notice the Contractor can serve a Notice of Determination. This will enable the Contractor to leave site, remove all its plant and equipment and then submit an account for all of the works carried out and materials supplied, including any claim for loss and expense. Question Answer From 1st October 2004, the Act requires service providers to make reasonable adjustments to the physical features of their premises, whether existing buildings or planned developments, where it is unreasonably difficult for disabled people to make use of the services provided. A service provider is someone who provides services to the public. The effects of the Act will be wide-ranging. It will be important to ensure that all works carried out to the premises of service providers comply with the requirements of the Act. The penalty for non-compliance is an action against the service provider for discrimination which could result in knock-on negligence actions against the builders or architects for inadequate building works or designs. If a court action is commenced, then the service provider will need to demonstrate that reasonable steps have been taken or that the failure to take what would otherwise be reasonable steps was justified. Existing premises must be to required standard by the October 2004 deadline and, therefore, service providers should start making preparations to comply with the requirements of the Act. Answer A basic rule of contract is the 'privity' doctrine which provides only those party to a contract may enforce it. Therefore, a person who subsequently acquires an interest in a particular development, such as a tenant, has little protection if he discovers that one of the original parties was negligent or acted in breach of contract. For example, a tenant having a full repairing lease may find a major design defect in the property and yet have no redress against the architect. This problem is overcome by the tenant insisting on collateral warranties from all those parties involved in the design and construction of the building he or she is leasing. If you are asked to enter into a collateral warranty, just remember you may be taking on additional liabilities which may be imposed by a stranger that you have not had any previous dealings with. Question Answer These contracts require the Contractor to provide the Architect or Quantity Surveyor `with all documents necessary for the purposes of the adjustment of the Contract Sum`. The contract provides a specified period for complying with this provision. Following receipt the Architect or Quantity Surveyor is required to prepare a statement of all adjustments to be made to the Contract Sum and following the preparation of the statement it is sent to the Contractor. The Architect/Quantity Surveyor has a limited period for preparing the statement. The statement produced by the Architect or Quantity Surveyor should show the total value of the works executed, together with any sums ascertained in respect of loss and expense. If the Contractor is not satisfied with the sum stated on the statement then he or she should challenge the content of the statement. It is important that any disagreement be made known at an early stage, as there is a possibility an Architect may include the final figure in the final certificate, and if the final certificate is not challenged within 28 days following issue then your right to challenge the figure may be lost.
|
|
|
ALL CONTENT COPYRIGHT ASHFORDS 2007, ALL RIGHTS RESERVED
|