|
|
||
|
Delay What Delay?IntroductionAn important decision was made by the Court of Appeal in the case of Shawton Engineering Ltd v DGP International Limited. The case concerned a sub-contract for design work concerning the construction of a process plant at Sellafield. The central issue to be determined by the Court concerned the circumstances in which one party to a contract may lawfully terminate the contract for delayed performance by the other party where that party's contractual obligation is to complete the work within a reasonable time and not by a fixed completion date. In this case Shawton employed DGP as sub-contractor to carry out design works and during the course of those works Shawton varied the scope of the works. As there was no extension of time mechanism in the sub-contract, the agreed completion date ceased to be relevant and the obligation upon DGP was to complete the works within a reasonable time. Shawton then wrote to DGP in November 2000 purporting to make time of the essence. When DGP had still not finished the design works by March 2001, Shawton terminated the sub-contract. The Court of Appeal made a number of findings as follows :-
The Court concluded that Shawton were wrong to terminate the sub-contract. Ashfords is regulated by the Solicitors Regulation Authority. The information in this article is intended to be general information about English law only and not comprehensive. It is not to be relied on as legal advice nor as an alternative to taking professional advice relating to specific circumstances.
|
|
|
ALL CONTENT COPYRIGHT ASHFORDS 2007, ALL RIGHTS RESERVED
|